Business, 17.02.2022 17:19
The people assigned to your project have high billable rates, and the project budget doesn t provide much of a buffer over your estimated total project cost. Fortunately, the project finish date has some wiggle room. Which measure of progress is most important to track in this situation? Select an actual work, remaining duration, actual start date, actual duration.